If you are looking for sap funds management implementation milestone and time line, you may go as below,

 

  • Project Phase:   Project Preparation        – 1 to 2 Weeks

                                Implementation Team Setup

                                Core Team identification

                                Project office / other setup

  • Project Phase:   Blueprints           – 2 to 4 Weeks

                                As Is and To Be discussion

                                To be process documentation

                                Gap Analysis

                                Sign Off

  • Project Phase:   Realization          8-12 Weeks

                                System Configuration

                                Development

                                Unit Testing

                                Integration Testing

  • Project Phase:   Final Preparation 4-6 Weeks    

                                User Acceptance Testing

                                User Training

                                Data Preparation

                                Data Migration / Communication

  • Project Phase:   Go Live & Support – On going

                                Go Live

                                Support

This time lines as been given on approx basis. This may vary depending upon complexity of the project and some other factors too.